When pouring concrete for side walls and columns, the concrete should be layered, and the thickness of each layer should not exceed 400mm.
The concrete for beams and slabs should be poured simultaneously, starting from one end and advancing forward.
The area should be minimized as much as possible during concrete pouring.
Attention should be paid to compacting the bottom and sides of the beam, and the vibrator should not directly touch the steel bars or embedded parts.
The virtual laying thickness of the concrete slab should be slightly greater than the thickness of the slab.
After vibration, it should be smoothed with a wooden trowel and then covered with plastic film.
The insulation layer should be promptly laid on top of it.
.