After the completion of the binding and installation process of the floor reinforcement, it is common to encounter situations on site where management personnel carry out inspection and acceptance work, and construction personnel frequently walk and directly step on the reinforcement during concrete pouring operations.
This behavior can easily cause the displacement of steel bars or cushion blocks, leading to quality problems such as excessive deviation in the thickness of the steel bar protective layer.
.