Guidelines for Selecting Good Materials – Assembling Integrated Composite Concrete Components

Building safe, comfortable, green and intelligent “good houses” is an important measure to improve building quality and meet the people’s demand for a better life.

Crown Foot Anchor

In order to fully leverage the supporting role of good materials for “good houses”, in accordance with the “Law of the People’s Republic of China on Science and Technology Progress” and the “Law of the People’s Republic of China on Promoting the Transformation of Scientific and Technological Achievements”, the Science and Technology and Industrialization Development Center of the Ministry of Housing and Urban Rural Development completed the second batch of building material product collection and release in 2026 based on the “Good House” construction applicable building material product collection work carried out in 2025, and included a total of 95 building material products from two batches in the “Good Material Selection Guide (2026)” for official publication.

The content of the “Guidelines” is now excerpted for display, providing reference for relevant units and individuals to understand and choose building materials products.

.

Application of anti-corrosion protection technology for concrete structures in building engineering

Concrete is the most essential structural material in building construction, with a hard and dense appearance, but there are numerous capillary pores inside the material.

Moisture, carbon dioxide, and salt ions can infiltrate into the interior of concrete through pores, causing concrete carbonation, internal steel reinforcement corrosion, and surface sanding and peeling.

Magnetic Thread Disc

The basement, exterior walls, outdoor steps, and first floor floors, which come into direct contact with water vapor, develop diseases at a faster rate.

Concrete anti-corrosion is different from ordinary wall painting.

The core goal is to seal the pores, block the infiltration of corrosive media, and protect the internal steel bars.

After many old buildings develop diseases, simple plastering and repair without blocking the penetration of the medium will continue to develop the diseases.

Understand the principle of concrete corrosion, distinguish the applicable scenarios of rigid protection, infiltration crystallization, surface sealing and other technologies, select appropriate solutions for different areas of the building, and achieve long-term protection of concrete structures.

.

Detailed explanation of each grade of concrete (strength grade, performance, purpose, and construction points)

The strength grade of concrete is determined according to the standard value of cube compressive strength.

Plastic Nail Plate

The standard value of compressive strength of a cube refers to the compressive strength value with a 95% guarantee rate measured by a standard test method on a 150mm side length cube specimen made and cured according to standard methods at 28 days or at the age specified in the design.

The guarantee rate of concrete strength grade is 95%, determined based on the principle of subtracting 1.

645 times the standard deviation from the average value of the overall distribution of concrete strength.

.

The provisions for load testing in the construction acceptance specifications cannot be used for safety appraisal load testing

3) For large components and components with reliable application experience, only crack width, crack resistance, and deflection tests can be conducted (large components generally refer to components with spans greater than 18m); Reliable application experience refers to the standard components produced by the unit that have been repeatedly applied in other projects, such as precast stairs, precast hollow slabs, precast double T slabs, etc.

Elephant Foot Ferrule

.

New regulation: Single component load test results can be used to evaluate the bearing capacity of similar components within the same batch

When conducting a house safety appraisal, for structures that have suffered damage due to fire, earthquake, or other reasons, or for components that have serious defects found during construction and use, as well as for structures with performance degradation and functional changes, such as floor cracking and steel corrosion, if investigation, testing, and verification analysis are not sufficient to evaluate the structural performance, load tests can be conducted to verify their actual structural performance indicators, providing a basis for further processing.

Steel Chamfer

For example, when evaluating the bearing capacity of cast-in-place floor slabs with a small number of non stress cracks, it is generally possible to analyze and judge the thickness, reinforcement, concrete strength, and crack distribution characteristics of the floor slab based on detection data and experience.

When there are a large number of non stress cracks in the floor slab, due to the existing conventional structural analysis techniques, it is not yet possible to quantitatively consider the impact of cracks on the bearing capacity and stiffness of the floor slab.

Load tests can be considered to accurately evaluate the structural performance of the floor slab.

.

Mechanism and preventive measures of shrinkage cracks in concrete of civil air defense basement

With the development of economic construction, a large number of civil air defense basements have been built, but there have also been many engineering quality problems, especially leakage problems, which are particularly prominent.

Lifting Socket

One important reason for water seepage is structural cracks.

Cracks not only have adverse effects on the sealing requirements of civil air defense engineering, causing water or toxic leakage, but may even develop into structural damage.

This article summarizes the common causes and preventive measures of shrinkage cracks in cast-in-place reinforced concrete, and verifies the effectiveness of the measures through engineering examples.

.

How to inspect the quality of concrete structures?

The structural entity inspection should be organized by the supervision unit and implemented by the construction unit, and the implementation process should be witnessed.

The construction unit shall develop a special plan for structural entity inspection and implement it after being reviewed and approved by the supervision unit.

The structural entity inspection items, except for structural position and dimensional deviations, should be completed by qualified testing institutions.

Plastic Rebar Chairs

In the inspection of structural entities, when the test results of concrete strength or steel reinforcement cover thickness do not meet the requirements, qualified testing institutions should be commissioned to conduct testing in accordance with the relevant national standards.

.