The production method of commercial concrete is different from other commodities, characterized by production based on sales and strong time constraints.
Once the concrete is produced, it is advisable to start unloading within 90 minutes and finish unloading within half of the initial setting time to ensure the quality of the concrete.
Therefore, the manufacturer and user must coordinate and ensure that the feeding speed is consistent with the material feeding speed, so that the concrete supply on the construction site is neither disconnected nor piled up.
.