(1) According to Article 9.
1.
1 of “Ready mixed Concrete” GB/T14092-2012, the quality inspection of ready mixed concrete is divided into factory inspection and delivery inspection.
The sampling and testing work for factory inspection shall be borne by the supplier, and the sampling and testing work for delivery inspection shall be borne by the purchaser.
When the demand side does not have the technical qualifications for testing and personnel, both parties can negotiate and entrust a qualified inspection unit to undertake it, and this should be clearly stated in the contract.
Article 9.
1.
2 stipulates that the delivery inspection results shall be notified to the supplier within 10 days after the end of the test.
Article 9.
1.
3 stipulates that the quality acceptance of ready mixed concrete shall be based on the delivery inspection results.
.