The original design requirement was to use mud wall protection to form holes, but due to site conditions, it was changed to a full steel casing for further drilling.
The designed pile diameter is 600mm and the steel casing diameter is 800mm.
When settling, is the concrete quantity calculated based on the designed pile diameter or the steel casing diameter?.